![](/images/install/1.jpg) |
– Slide top landing over pole and fasten in position in well opening |
|
![](/images/install/2.jpg) |
– Level centre pole and fasten to floor |
|
![](/images/install/3.jpg) |
– Remove landing and pass each tread one-by-one over topof pole and form a stack at base |
|
![](/images/install/4.jpg) |
– Re-install landing into appropriate position |
|
![](/images/install/5.jpg) |
– Slide top tread back up pole to designated height
– Level out spindle and fasten tread to centre pole
– Repeat with remaining treads |
|
![](/images/install/6.jpg) |
– Start from the top and fasten handrail to each spindle using butterfly nuts
– Pre-drill handrail with 1/8″ drill bit
– Re-drill with 3/8″ drill bit in order to pass toggle head through pipe handrail |
|
KEEP IN MIND: your stair kit will include one spindle per riser. Two of the spindlers are thicker than the rest (3/4″ sq). They will be the first and last spindle on the staircase. The bottom spindle may require cutting. |